Interiors work progress of S2 Speed Tower

Dear Friends,

Please to share interiors work progress of S2 Speed Wing Tower, as shared by builder, as on 25-08-2019.

1. Block Work 17th Floor Completed.
2. Railing ( Balcony Grill) One Side 17th floor & other Side 14th floor.
3. CPVP Work Toilet 15th floor Completed.
4. Wall Conduit 7th floor in Progress.
5. Chaukat fixing 9th floor Completed.
6. Inside Plaster 5th floor going on oneside & 3rd floor Other Side.
7. External Plaster- Scaffolding Started.

Similarly parrel interiors are going on in S3 & S4 Towers. Details of same will be shared once received.S2 20th floor finishing detail Table dt 28.8.19

Categories
Society News

Archetect Certificate for 4th floor of S5 & 20th floor of S4 Tower, Aug 19

Categories
Le Solitaire Society News

Actual site pics of 3 bhk towers on 15.8.19 possesion in first quater 2020

Categories
Area Updates Delhi Real estate Le Solitaire Society News Testimonials

Mrs Deepa Sinha w/o Former Chairman Bihar Public Service Commision

Categories
Society News

Construction Certificates May 19,S4 19th floor, S3 18th floor,S5 3rd floor

Categories
Society News

Construction Certificate of S2 & S5 Tower ,April 2019

S5-2nd Floor Archetect Certificate

S2-18th Floor Archetect Certificate

Categories
Le Solitaire Society News

Construction pictures of towers S2,S5,T2 & T4 as on 28.3.19

Categories
Le Solitaire Noida Area Society News

Construction pictures & updates of March 2019,3 BHK towers structure nearing completion

Solitairian City Letter for Updation for all towers details.
Categories
Le Solitaire Society News

Work resumes on T4 tower with laying of 5th floor slab