S4 Tower certificate for top floor has been issued now after some work has resumed under the Covid 19 lockdown 4. The tower was completed on March 18,2020.

Tower S4 top floor Certificate

News Letter – Solitairian City (020220)

Categories
Le Solitaire Society News

Feburary 2020 News letter for construction progress by Builder

News Letter – Solitairian City (020220)

Categories
Le Solitaire Society News

Finishing of 2BHK Flat in Turbo Tower T1 flat Started. This will be for time being used as office. Members will also get to see how actual flat will look

Categories
Le Solitaire Society News

Areial Veiw of F1 car sport stadium

Categories
Society News

Members on Solitaire site for Plantation Day on 14.11.19.

Categories
Society News

Construction Status Report by Builder as on 10.11.19 for Speed Towers S2,S3,S4

S2 status 13.11.19S3 status 13.11.19S4 status 13.11.19

Categories
Area development Society News

S2 Top Floor completion certificate

Categories
Society News

External Plaster starts in Towers S2-3-4 3 BHK towers

Categories
Society News

Tower S3 20 th floor Archetect Certificate

S3-20th Floor Archetect Certificate

Categories
Le Solitaire Society News

S3 & S4 Towers Construction Progress

D. P. R on dated:-18/09/2019 – (S4)

slab&col- 60% column casting complete of 21st floor

Block Work – 18th Floor (95% Complete) 17th Floor Ongoing (80% complete)
CPVC Work Toliet- 16th Floor (90% Complete) kitchen work on progress
Chaukhat – 9th Floor complete, 10th on progress
Plaster Inside – 3rd and 4th Floor Ongoing
Electrical Conduting Work – 12th Floor (100% Complete), 13th Floor On-Going
Scaffolding- on progress

D. P. R on Dated :- 16-09-2019 (S3)

slab & Columns –
19th floor slab(100%) completed.
20th floor slab steel binding is on going (50%completed)

Block Work –
18th Floor (100% Complete)
19th Floor Ongoing

CPVC Work Toliet & kitchen-
17th Floor (100% Complete)

Chaukhat –
10th floor comoleted
11th Floor on going

Plaster Inside –
2,3,4th floor completed.
5th and 6th Floor is On going .

Electrical Conduting Work –
12th Floor (100% Complete).
13,14,15th Floor is On-Going.

Railing work-
Front side :-
till 17th floor completed.
Back side:-
1st portion till 17th floor completed.