S3 & S4 Towers Construction Progress

D. P. R on dated:-18/09/2019 – (S4)

slab&col- 60% column casting complete of 21st floor

Block Work – 18th Floor (95% Complete) 17th Floor Ongoing (80% complete)
CPVC Work Toliet- 16th Floor (90% Complete) kitchen work on progress
Chaukhat – 9th Floor complete, 10th on progress
Plaster Inside – 3rd and 4th Floor Ongoing
Electrical Conduting Work – 12th Floor (100% Complete), 13th Floor On-Going
Scaffolding- on progress

D. P. R on Dated :- 16-09-2019 (S3)

slab & Columns –
19th floor slab(100%) completed.
20th floor slab steel binding is on going (50%completed)

Block Work –
18th Floor (100% Complete)
19th Floor Ongoing

CPVC Work Toliet & kitchen-
17th Floor (100% Complete)

Chaukhat –
10th floor comoleted
11th Floor on going

Plaster Inside –
2,3,4th floor completed.
5th and 6th Floor is On going .

Electrical Conduting Work –
12th Floor (100% Complete).
13,14,15th Floor is On-Going.

Railing work-
Front side :-
till 17th floor completed.
Back side:-
1st portion till 17th floor completed.