Dear Friends,
Am pleased to share above as provide by CRM- Solitairian City, for your kind perusal.
Block Work – 18th Floor (100% Complete) 19th Floor Ongoing
CPVC Work Toliet- 15th Floor (100% Complete)
Chaukhat Fixing – 11th Floor Completed
Plaster Inside – 7th Completed and 8th Floor Ongoing
Electrical Conduting Work – 10th Floor (100% Complete), 11th Floor On-Going
Scaffolding- Complete for the entire tower