UP Chief Secretary holds Jewar International Airport meeting & the following Orders were passed.
1. Existing Techno-Economic Feasibility Report accepted. This will save 6 months for Airport to become operative.
2. Authority directed to finalise Nodal Agency to make Detailed Progress Report. One PCS officer already appointed to execute land procurement.
3. Authority directed to initiate land accusation.
4. Total fund’s of Rs. 3000 crore sanctioned for accruing 1000 acres.
5.
7. HUDCO offers entire Rs. 3,000 funds @10%.
8. NCR planning board offers only Rs. 500 crores @ 7.5%
8. International Routes connecting to Far-East & Eastern Countries will be operative from starting of Airport so as to make it International Airport from day one.